Friday, October 3, 2008
House Photos (Oct. 2, 2008)
I've had a few requests to post some photos of the house, so for your viewing pleasure may I present to you... "Our House". Click on the photo for an enlarged view.
Thanks for watching.
Saturday, September 13, 2008
Monday, July 28, 2008
Monday, July 28th, 2008 (pool is full)
Well we have a totally filled pool. WOW... I can not believe it only took 2 day, 2-1/2 hours to full 31,500 gallons! We must have a good water well. Knock on wood. We have FTW Custom coming out tomorrow to pour 16 gallons of acid in and we start our two-a-day brushing for the next three days. Then on Friday, FTW Custom comes and fires up the pump and filter to get this bad boy clean.
Tonight we also went for a 1 hour swim. It felt Grrrrreat!!! We wanted to swim before the acid bath so tonight was the night. The jump rock was good, the swim outs were nice, and it just couldn't have been any better.
Anyone thinking of getting a pool I say... HURRY UP!!!... and call FTW Custom pools for what we feel is a good deal.
Sunday, July 27, 2008
Sunday, July 27, 2008 (Filler up)
Day 13 - Saturday, July 26, 2008 (plaster complete)
We have plaster in the pool and water is pouring in. Other than getting a late start to the day, everything went perfect. We were taken a back by the nasty gray color of the plaster as it sprayed out the hose but were assured that after an acid bath and a bit of scrubbing twice a day for three day that the true colors would come out. Lets hope so.
The pool and spa started filling at 2:00 PM... one hose in each. At 4:30 the 500 gallon spa was full so that hose was then put into the pool along with the other hose. At 1000 gallons (2 hoses pumping 500 gallons of water every 2.5 hours) every 2.5 hours I figure the pool should be filled at around 10:00PM Tuesday night. It'll be interesting to see how far my calculations are off.
After the pool is full Kirk, from FTW Custom comes and dumps 16 gallons of Muratic acid into the water. The 2-a-day stirrings start. After 3 days of that Kirk comes back out and fires off the equipment and we start cleaning the water. Once the water gets clear it's time to go for a bunch of swims. WHOO-HOO!!!!!!
It'll be nice to have my backyard back again.
Thursday, July 24, 2008
Day 12 - Thursday, July 24, 2008 (cleanup complete)
The workers showed up yesterday and graded the yard around the pool, finished the rock waterfall, pumped all the old nasty water out, and cleaned inside the pool. All this is in prep of the plaster guys to come out. Looks like that will happen this Saturday morning. Then we start filling er up with water.
We'll keep you informed as we get continue to get closer to startup.
Monday, July 21, 2008
Day 11 - Monday, July 21, 2008 (deck poured)
Thursday, July 17, 2008
Day 10 - Thursday, July 17, 2008 (form it up!)
Wednesday, July 16, 2008
Day 9 - Wednesday, July 16, 2008 (finished rock waterfall???)
Doubtful.
The wall looks... OK, but I think it needs a bunch of tweaking. It's too flat on top and weak at the right end. Contractor says it wont be a problem to put some more rocks where needed, but wants to do it after the deck is in so we can get an accurate look it.
Deck is suppose to get framed out and completed tomorrow. Keep your fingers crossed.
See ya on Day 10.
Tuesday, July 15, 2008
Day 8 - Tuesday, July 15, 2008 (rocks, rocks, and more rocks)
Work continued today on building the rock waterfall. NO, they did not get done today like we were told. The jump rock has been set and the waterfall should be complete tomorrow.
The deck guy came out and marked off the perimeter for the deck. Of course we wanted it larger and it will cost more, but nows the time to do it while they are here doing it.
Stay tuned pool fans.
Subscribe to:
Posts (Atom)